1. Hardware

In this week the hardware part some new problems have arisen, when the systerm is energized the plane will suddenly turn backwards, which is almost destory the systerm.

Finally we found that it is caused by the heavy  blanacing weight, when the arm of force is too small, the counterweight block will forcibly drag the plane causing the plane to lean backwards.

We waive the solar panel and reduced the weight the problem be solved temporary.

Here is the physical circuit we used in the test:

 


2. Software

In this week the software part do not have too much modify, so we spend more time on test the hole system, we solved some problem we found during the test one is the sensitivity of photoresistors and the other one is the shake of the sevor.


3. Test

we tested the systerm to mak sure the systerm can meet the basic requirements.

 


The acture circuit we used in the systerm is the picture below:

The LED part is remove from the systerm because we donnot have enough wire to connect all the components, and we add one more photoresistance to make sure the  light tracking part has higher fault tolerance, in this way each sevor is controled by two photoresistances there will be no conflict between them.

In the end, we decided not to install solar panel because the cardboard frame structure we were using was not enough to support the weight of the solar panels and carry it turn around.